The Daily Monitor (Addis Ababa)

Ethiopia: AfDB Set to Start Funding Gibe III - Report

5 July 2009


Addis Ababa — The African Development Bank (AfDB) is making preparations to start funding the Gibe III dam, a mega project on River Omo whose completion is expected to alleviate electricity crisis in the region, according to a report on Friday.

The bank is conducting technical, economic and financial assessments of the project to start the works by end of year, Business Daily reported citing AfDB's director in charge of infrastructure, Gilbert Mbesherubusa, as saying.

"The project will bring electrical energy to Ethiopia, Kenya and neighbouring countries, thus contributing to regional economic development and poverty alleviation," the director was quoted as having said.

The report said however, activist groups around Lake Turkana have been mounting campaigns against the project, saying it will affect the ecosystem.

"Apart from AfDB, the World Bank and European Investment Bank are some of the financiers that the lobby - Friends of Lake Turkana - has been targeting" The same group of financiers was also expected to support the construction of power transmission lines between the two countries to facilitate electricity importation, the daily added.

"AfDB says it accepted to fund the project after a full scale environment and social impact assessment cleared it." "And in line with our policy of financing only the socially acceptable projects, we have an ongoing dialogue with local communities to be affected by the project," the report quoted Mbesherubusa.

The construction of the whole project is expected to cost €1.55 billion is already 32 per cent complete.

The Kenyan media said it was not immediately clear which proportion of the remaining phase of the project will be funded by AfDB.

The hydro-plant is designed to generate 1,870 megawatts of electricity once completed and commissioned in 2013, making it the largest dam in Ethiopia.

This could relieve Kenya's investors who have had to bear the brunt of climate change which has drastically reduced the country's hydro electric power generation potential.

Be the first to Write a Comment!

More News on allAfrica.com

Copyright © 2009 The Daily Monitor. All rights reserved. Distributed by AllAfrica Global Media (allAfrica.com). To contact the copyright holder directly for corrections — or for permission to republish or make other authorized use of this material, click here.

AllAfrica aggregates and indexes content from over 125 African news organizations, plus more than 200 other sources, who are responsible for their own reporting and views. Articles and commentaries that identify allAfrica.com as the publisher are produced or commissioned by AllAfrica.

AllAfrica - All the Time


Sign up for FREE daily 'top headlines' by email »


SELECT
SELECT

Most Active Stories: Ethiopia

Topics